•
19 June 2009:
ITER Council endorses phased approach to the completion of ITER
On 17-18 June, the ITER Council, the Governing Body of the ITER Organization, convened for its fourth meeting. The two-day meeting in Mito,
Japan brought together representatives from the seven ITER Members: China, the European Union, India, Japan, Korea, Russia and the United States.
The ITER Council endorsed as a working basis for development of the project baseline the phased approach to the completion of ITER construction and the
target date for First Plasma by the end of 2018, maintaining operation with Deuterium and Tritium fuels in 2026. The Council also requested the
finalization of a realistic schedule with the resources needed to complete ITER construction. In order to substantially reduce overall risk the primary
components of the ITER machine will be assembled and tested together before the progressive installation of in-vessel components continues.
More information
Standpoint of the European Commission